Projects
Green Growth Planting is a Sydney-based contractor delivering efficient, high-standard planting solutions across civil, commercial, and environmental projects. We partner with builders, landscapers, and government bodies to install native and ornamental landscapes—on time, on spec, and with crews who get it done.
Our portfolio demonstrates our proven capability in managing diverse project scales, adhering to strict timelines and budgets, and navigating complex site conditions. We are committed to achieving exceptional environmental and aesthetic outcomes while ensuring efficient project execution.
Project 1: Ecological Restoration, Mass Planting
Project Type: Bush Regeneration / Civil Landscaping Planting
1. Principal Client
-
Client Name: Muru Mittigar
-
Client Sector: Environmental / Land Management / Community (Note: Muru Mittigar is an Aboriginal social enterprise focusing on land management)
2. Location & Scale
-
Site: Fleet St, Parramatta; North Urban Renewal Area
-
Area/Length: Multi-stage planting project involving a total of 14,466 units across various plant types (Tubestock, Nursing Tube, Forestry Tube). Area size: 4822 sqm.
3. Duration
-
Start Date: April 2025 (Stage 1)
-
Completion Date: May 2025 (Stage 3 Completion)
-
Maintenance Period: Nil
4. Budget
-
Total Project Value: AUD 1-20,000.00
-
Key Cost Components: Plant Installation (Tubestock, Nursing Tube, Forestry Tube), Planting Labour (Set out, On-site transport, Terraform/Fertiliser Application.
5. Scope of Works
-
Project Objective: Large-scale staged revegetation/planting within the Fleet St Parramatta North Urban Renewal area, encompassing diverse plant types and ground conditions.
-
Key Activities Performed (Across 3 Stages):
-
Planting & Ground Conditions:
-
Total 14,466 units planted, comprising:
-
Tubestock (un/semi-compacted ground, set out, on-site transport, terraform/fertiliser application): 2186 (Stage 2) + 2820 (Stage 3) + 1660 (Stage 1) = 6666 units
-
Nursing Tube (un/semi-compacted ground, set out, on-site transport, terraform/fertiliser application): 2936 (Stage 2) + 0 (Stage 3) + 0 (Stage 1) = 2936 units
-
Forestry Tube (un/semi-compacted ground, set out, on-site transport, terraform/fertiliser application, mulch application): 2715 (Stage 3) + 2149 (Stage 1) = 4864 units
-
-
Application of Terraform/Fertiliser with planting
-
Installation with mulch
-
Consideration for compacted vs. un/semi-compacted ground conditions during planting.
-
-
On-site logistics: Set out and on-site transport of plants.
-
6. Outcomes & Lessons
-
Key Achievements:
-
Successful installation of a significant volume of diverse plant species (over 14,000 units), contributing to the revegetation of the Parramatta North Urban Renewal area.
-
Demonstrated capability in managing multi-stage planting projects with varying ground conditions.
-
Effective coordination of plant logistics and labour for large-scale operations.
-
-
Challenges & Solutions:
-
General Challenges: Site variations (downtime, delay, additional ground covers) require notice to Green Growth Planting.
-
Challenge: Managing high volume plant delivery and storage across multiple project stages to avoid congestion.
-
Solution: Implemented just-in-time delivery for specific plant types per stage and utilized designated holding areas.
-
-
Lessons Learned for Future Projects:
For multi-stage projects of this scale, pre-planning of ground condition variations and plant type logistics is crucial for efficient execution and minimal downtime.
7. Contact for Reference:
Daryl Wells – Open Spaces Manager
Email: Daryl.Wells@Murumittigar.com.au | Phone: 0487111158
Project 2: Civil Landscaping, Mass Planting (Multi-Stage)
Project Type: Mixed (Civil Landscaping Planting & Maintenance)
1. Principal Client
-
Client Name: Gauci Civil + Camden Local Council
-
Client Sector: Commercial Developer / Civil Contractor
2. Location & Scale
-
Site: 1E Fairwater Dr, Harrington Park Reserve, Harrington Park, NSW
-
Area/Length: 3.69 ha
3. Duration
-
Start Date: September 2024
-
Completion Date: November 2024
4. Budget
-
Total Project Value: AUD 20,410.00
-
Key Cost Components: Landscape Plan Design, On-Site Plant Transport + Set-Out, Plant Installation, Post-Planting Care including Fertiliser Application and Stakes + Tie Installation.
5. Scope of Works
-
Project Objective: Provide timely civil landscape-mass-planting at a high-quality standard for areas within the Harrington Park development.
-
Key Activities Performed:
-
Landscape Plan Design
-
Interpret preliminary landscape designs
-
Re-design 2D model of plant set-out in adjustment to on-site deletions, variations and additional garden beds
-
-
Mass Planting Installation:
-
Install tubestock (928.00 units)
-
Install nursery pots from 140mm to 300mm in size (9622.00 units)
-
Install street-trees from 45LTRs to 200LTRs in size (102.00 units)
-
-
6. Outcomes & Lessons
-
Key Achievements:
-
Successfully executed specified mass planting for all designated areas.
-
Provided timely and cost-effective solutions for the installation of over 10,000 planting units within the span of 8 production days with a crew of 5 planters.
-
Practical Completion / Hand-Over: (3-Month Post-Planting) >95 percentile survival rates.
-
-
Challenges & Solutions:
-
Larger sizes of street-trees required more intensive soil preparation than initially estimated with imported soil (approx. 300mm) being too shallow and hitting the site’s subgrade. Solution: Utilised client’s on-site heavy machinery to excavate past the subgrade, meeting planting depth requirements, thereby managing completion of planting works to within initial timeframe.
-
Certain areas of the site were not prepared for mass-planting. Solution: Plant supply and installation was scheduled for 2-stages, allowing for greater program efficiency.
-
-
Lessons Learned for Future Projects:
-
Enhanced pre-site soil analysis can better inform initial material estimates for amelioration.
-
Certain species were found to have high mortality rates despite correct plant-installation techniques after a period of 3 months of being planted.
-
Lesson: Improve pre-planting soil analysis including pH testing, to ensure plant species can properly establish and survive in the long-term.
-
7. Contact for Reference:
Chris Gauci – Director, Gauci Civil
Email: chris@gaucicivil.com.au | Phone: 0412 345 678
Frequently Asked Questions
Q: What types of projects have you completed?
Our experience covers all planting-related projects from mass revegetation bush regeneration, civil landscaping and commercial green-industrialisation. We specialise in all planting projects and quote according to complexity, volume and scope of works.
Q: How do you manage large-scale projects and ensure quality on complex sites?
Our managers provide a predictable and structured approach, from detailed planning, pre-site assessments, and QA protocols throughout the planting program to ensure transparency and communication. Our experienced teams oversee every phase—from initial planning and installation to ongoing maintenance—ensuring that each project meets our stringent quality and compliance standards.